GH Aquatic & Gym / Item 4.2
Roof plant — air cooled chiller R2, PowerPax system with twin compressors
CAP
Moderate
Asset Details
Discipline:Mechanical Services
Subject Type:Plant & Equipment
Location:GH Aquatic & Gym
Condition Assessment
Condition:
Fair
Recommendation:
Replace with R1 as coordinated project. Budget for both units together.
Financial Summary
10-Year Total:$489k
Near-Term (CY25–26):$489k
Work Type:
Capital
Year-by-Year Cost Schedule
Planned expenditure by calendar year
| Year | CY2025 | CY2026 | CY2027 | CY2028 | CY2029 | CY2030 | CY2031 | CY2032 | Total |
|---|---|---|---|---|---|---|---|---|---|
| Spend | — | $489k | — | — | — | — | — | — | $489,000 |
Condition & Recommendation
Condition Assessment
Fair
Full Recommendation
Replace with R1 as coordinated project. Budget for both units together.
Linked Items
Related Risk
None linked
Related Work Orders
None linked
Related Projects
None linked
Item reviewed — June 2025 SAMP update
Cost estimate updated
Item added to SAMP