JAPAC Building

Senior School

BLDG-JAPAC • Last updated June 2025

10-Year CapEx

$3.6M

R&M:$2.0M (57%)
Capital:$1.5M (43%)
Timeline
Near-term (Yr 1–2):$1.4M
Medium-term (Yr 3–5):$605k
Long-term (Yr 6–10):$1.6M
Risk Profile
Highest risk:
Moderate

0 High/Very High items

Next major expenditure: CY2026

ItemDescriptionConditionTypeRiskNear-Term10-Yr TotalActions
2.2.1

Level 5 roof — metal sheeting, colorbond cladding, box gutters, safe access walkways and anchor points

Fair - Good
R&M
Moderate
$48k$237kView
4.1

Mechanical services — complete review and redesign of plant to address air quality and humidity levels

Fair
CAP
Moderate
$490k$490kView
4.2

Plantroom — 2x air cooled chillers (2017), 238kWr each

Fair
CAP
Moderate
$430k$430kView
4.7

Roof plant — 17x VRF heat recovery split systems (ducted and cassette types, 2018)

Good
CAP
Low
$0$390kView
7.1

Hydraulic services — domestic cold and hot water, sanitary drainage, stormwater

Good
R&M
Low
$20k$99kView

Year-by-Year Spend

R&M vs Capital expenditure for JAPAC Building

SAMP updated — June 2025 review

Building added to platform